Leisure

Client: St Patrick’s GAA Club, Cloneen
Civil Sub-Contractor: ESK Plant Ltd
Contract Duration: 3 months.
Construct new walkway to perimeter of Cloneen GAA ground.

Scope of Works

  • Clear the route of spoil and overgrown trees
  • Construct a 500meter walking path to the perimeter of the GAA ground including lighting and future ducting provision.
  • Finished the top surface with a coat of Ballylusk dust to give a durable weather resistant walking surface.
  • Landscaped all surrounding areas on completion

EQUINE:GALLOP CONSTRUCTION AND INSTALLION OF LIGHTING

Client:  Various private customers
Civil Sub-Contractor: ESK Plant Ltd
Contract Duration: 2months.
Upgrade/construction of all-weather gallops, comprising of complete drainage and ducting system.

Scope of Works

  • Trench Works and Installation of ESB Ducting / Bases and Sleeves for Light Poles

SPORTS PITCHES

Client: Clonmel Town FC
Civil Sub-Contractor: ESK Plant Ltd
Contract Duration: 12 months.
Redevelopment of the existing grounds

Scope of Works

  • Constructed a new 100 x 50 training pitch on an elevated platform on what was previously waste ground
  • Repositioned the existing main pitch to allow for the construction of a youth training area along with an exercise area
  • All playing surfaces were designed and constructed to the highest FAI standards