EQUINE: CONSTRUCTION OF 100m MULTI PURPOSE BUILDING

Duration of Works: 6 weeks

Scope of Works:

 

  • Cleared and graded site to ensure proper leveling and drainage.
  • Installed concrete pads for structural support.
  • Laid foundations for the shed base and front yard.
  • Erected the main structural framework.
  • Installed exterior sheeting and roofing materials.

 

Completing this 100mx18m multipurpose building and yard from a greenfield site in just six weeks was a significant achievement for our team. We efficiently cleared and graded the site, installed concrete pads for structural support, and laid the foundations for the shed base and front yard. The main structural framework was erected with precision, and exterior sheeting and roofing materials were installed seamlessly. This project demonstrates our team’s capability to handle large-scale construction projects effectively and on time.

 

 

SPORTS: CONSTRUCTION OF NEW WALKWAY AT CLONEEN GAA

 

Client: St Patrick’s GAA Club, Cloneen

Contract Duration: 3 months

Scope of Works

  • Cleared the route of spoil and overgrown trees.
  • Constructed a 500m walking path around the perimeter of the GAA ground including lighting and future ducting provision.
  • Finished the top surface with a coat of Ballylusk dust to give a durable weather resistant walking surface.
  • Landscaped all surrounding areas on completion.

 

EQUINE: GALLOP CONSTRUCTION AND INSTALLATION OF LIGHTING

Contract Duration: 2 months

Scope of Works

  • Trench works and installation of ESB Ducting/Bases and sleeves for light poles.
  • Upgrade/construction of all-weather gallops, comprising of complete drainage and ducting system.

SPORTS: REDEVELOPMENT OF CLONMEL TOWN FC GROUNDS

Client: Clonmel Town FC

Contract Duration: 12 months

Scope of Works

 

  • Constructed a new 100m x 50m training pitch on an elevated platform on what was previously waste ground.
  • Repositioned the existing main pitch to allow for the construction of a youth training area along with an exercise area.
  • All playing surfaces were designed and constructed to the highest FAI standards.